Area of Logistics and Industrial Activities of Asturias.
Gijón, Asturias.
With four million m² and a budget of €150 million, it was going to be the most important industrial area in northwest Spain. The civil works of the first phase (one million m²) finished in 2013, but companies cannot move in because the area lacks proper road connections and a reliable power supply. Only one of the 60 plots has been sold, which is jeopardizes its viability, because from 2015 the public management company has to repay a loan of €90 million, and it has no income to be able to do it.